[159309] in Hotline Meeting
Approved Bldg. 66 - (see listing below for specific areas) - Air
daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue Jun 5 12:36:07 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "wdalzell@MIT.EDU" <wdalzell@mit.edu>,
"hammond@MIT.EDU"
<hammond@mit.edu>,
"kfjensen@mit.edu" <kfjensen@mit.edu>,
"alimart@mit.edu"
<alimart@mit.edu>,
"Swetzel@mit.edu" <Swetzel@mit.edu>,
"OPS RM Campus
Services East" <rm-ecs@mit.edu>,
Ops Custodial Admin & Support Staff
<cust-staff@mit.edu>,
"gillooly@MIT.EDU" <gillooly@mit.edu>,
"wayneb@mit.edu"
<wayneb@mit.edu>,
MIT Schedules Office <schedules@mit.edu>,
"barnard@mit.edu"
<barnard@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>,
Ops RM Shutdown
<rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
"DOF
Customer Service Center" <dof-csc@mit.edu>,
"Ops Custodial Admin & Support
Staff" <cust-staff@mit.edu>,
Billy Homeyer <whomeyer@plant.mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>
CC: "jcombs@mit.edu" <jcombs@mit.edu>
Date: Tue, 5 Jun 2012 12:36:03 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE2AA0179@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved air handler 2, 5, and 1 (return fans 2 and 3) shutdown for Bldg. 66 - (see listing below for specific areas, on Wednesday, June 6, 2012, scheduled times listed below, is for your information. Any questions, please contact Billy Homeyer, x8-0432.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: June 6, 2012
Day: Wednesday
Time: please see scheduled times below
Building(s): 66
Room(s): see listing below for specific areas
System: Air Handler 2, 5, and 1 (Return Fans 2 and 3)
Duration: 2 hours each air handler
Reason:
We request bldg 66-AH2, AH5 and AH1 w/RF's 2 and 3 shutdowns on Wednesday, June 6th, 2012 as follows; AH2 from 6 AM to 8 AM (serves flr 1-5 office/classroom induction units), AH5 from 8 AM to 10 AM (serves 110), AH1 and return fans 2 and 3 from 10 AM to noon for Shawmut Construction (Dan Cook 617-908-6990) and Ducts Inc (Darren King 617-908-7370) to continue inspecting ductwork and fire dampers as part of the 66-steam leak recovery project. Bill Vitkosky 3-6517 and Jennifer Combs 3-7671 are the MIT project managers.
Schedule:
AH2 from 6 AM to 8 AM (serves flr 1-5 office/classroom induction units),
AH5 from 8 AM to 10 AM (serves 110),
AH1 and return fans 2 and 3 from 10 AM to noon
Effect:
Loss of supply ventilation and cooling air for the duration of the shutdown.