[159306] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 66 - All, Domestic Hot and Cold Water Shutdown Request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue Jun 5 11:09:10 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <koskae@MIT.EDU>
Date: Tue, 5 Jun 2012 11:09:06 -0400
Message-ID: <0196455FDC88465A8129B3F6951A491A@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following domestic hot and cold water shutdown request for Bldg. 66 - All, on Wednesday, June 6, 2012, 6:00am - 8:00am, is for your information and response.  Any questions, please contact Billy Homeyer, x8-0432.

Please let us know whether this does or does not have your approval.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381

Type: Normal
Date: June 6, 2012
Day: Wednesday
Time: 6:00am - 8:00am
Building(s): 66
Room(s): All
System: Domestic Hot and Cold Water
Duration: 2 hours
Reason: 
We request a bldg 66-all domestic water shutdown from 6 AM to 8 AM on Wednesday,
June 6th, 2012 for PJ Dionne Plumbing (Paul Dionne 978-657-3990) to cut/cap and install new isolation valves on the h/c domestic water feed (and hot water return) to the closed 1st floor restrooms and as part of the Prof. Tisdale Lab renovation project by Elaine Construction (Nick Murray 617-799-7913). Evan Koska 4-6173 and Kim Sutherland 8-5962 are the MIT project managers.

The shutdown is written up for 66-all under the assumption that any local 1st floor isolation valves will not hold.


Effect: 
Loss of domestic hot and cold water for the duration of the shutdown.

home help back first fref pref prev next nref lref last post