Bldg. 35 - Basement, Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue Jun 5 09:46:02 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <mmcorrei@MIT.EDU>
Date: Tue, 5 Jun 2012 09:45:56 -0400
Message-ID: <514E7822A39947B99CEFE0E19D99467D@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following chilled water shutdown request for Bldg. 35 - Basement, on Wednesday, June 6, 2012, 8:00am - 12:00pm, is for your information and response. Any questions, please contact Mike Correira, x8-9174.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: June 6, 2012
Day: Wednesday
Time: 8:00am - 12:00pm
Building(s): 35
Room(s): Basement
System: Chilled Water
Duration: 4 hours
Reason:
to tie-in the chilled water line to the lab
Effect:
Loss of chilled water for the duration of the shutdown.