CANCELLED - Bldg. 16 - 7th Floor, Tempered Water (for eyewash and
daemon@ATHENA.MIT.EDU (Janine Findlay)
Mon Jun 4 08:52:04 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "ddarling@mit.edu" <ddarling@mit.edu>, "dudley@mit.edu" <dudley@mit.edu>,
"hsinhwa@MIT.EDU" <hsinhwa@mit.edu>,
"sorrento@MIT.EDU" <sorrento@mit.edu>,
"nsteele@mit.edu" <nsteele@mit.edu>, "thilly@mit.edu" <thilly@mit.edu>,
"jdoughty@mit.edu" <jdoughty@mit.edu>, "swade@mit.edu" <swade@mit.edu>,
"rjwilk@mit.edu" <rjwilk@mit.edu>, "jmganno@MIT.EDU" <jmganno@mit.edu>,
"pcog@MIT.EDU" <pcog@mit.edu>, "galanek@mit.edu" <galanek@mit.edu>,
"bobk@mit.edu" <bobk@mit.edu>, "nmorriso@mit.edu" <nmorriso@mit.edu>,
"OPS
RM Campus Services East" <rm-ecs@mit.edu>,
Ops Custodial Admin & Support
Staff <cust-staff@mit.edu>,
"carleton@mit.edu" <carleton@mit.edu>,
"pearlin@mit.edu" <pearlin@mit.edu>,
"mcpierce@MIT.EDU" <mcpierce@mit.edu>,
"wturner@mit.edu" <wturner@mit.edu>, Gerry Hughes <ghughes@mit.edu>,
"lechtman@mit.edu" <lechtman@mit.edu>, "Tarky@mit.edu" <Tarky@mit.edu>,
"MIT
Schedules Office" <schedules@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"kasabula@mit.edu" <kasabula@mit.edu>,
"ksimons@mit.edu" <ksimons@mit.edu>, "daczel@mit.edu" <daczel@mit.edu>,
"rweinrib@MIT.EDU" <rweinrib@mit.edu>,
"worklife@mit.edu" <worklife@mit.edu>,
"rsimpson@mit.edu" <rsimpson@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
Ops RM Plumbing Team
<rm-plumbing@mit.edu>
CC: "erita@mit.edu" <erita@mit.edu>, "jcclark@mit.edu" <jcclark@mit.edu>,
"kccarty@mit.edu" <kccarty@mit.edu>
Date: Mon, 4 Jun 2012 08:52:01 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE29BEE23@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following tempered water (for eyewash and safety showers) shutdown request for Bldg. 16 - 7th Floor, on Monday, June 4, 2012, 9:00am - 1:00pm, has been cancelled and will be rescheduled at a later time. Any questions, please contact Keith Carty, x3-4948 and ask to have him paged.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: June 4, 2012 *CANCELLED - will be rescheduled
Day: Monday
Time: 9:00am - 1:00pm
Building(s): 16
Room(s): 7th Floor
System: Tempered Water (for eyewash and safety showers)
Duration: 4 hours
Reason:
to install isolation valves
*CANCELLED - will be re-scheduled - we did not have full customer approval and therefore will re-schedule the shutdown for a better time. Thank you.
Effect:
Loss of tempered water (for eyewash and safety showers) for the duration of the shutdown.
*CANCELLED - will be rescheduled