[159196] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg 32 - Room D475. Sprinkler Shutdown Notification

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu May 31 11:28:43 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jackc@csail.mit.edu>
Date: Thu, 31 May 2012 11:28:04 -0400
Message-ID: <34782EA58DE54CE7A5196B952A7C9FF9@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following sprinkler shutdown notification for Bldg 32 - Room D-475 on Friday, June 1, 2012, from 7:30-4:30, is for your information. No response is required to this notification. Any questions, please contact Jack Costanza x 3-6303.

We appreciate your patience while the repairs/renovations are in progress.

Thank you,

Chris Gilbert
Operations Center

The Safety Office will be advised of this and notify the Fire Department.


Type: Normal
Date: June 1, 2012
Day: Friday
Time: 7:30 -4:30
Building(s): 32
Room(s): D475
System: Fire Protection Water 
Duration: 9 hours
Reason: 
Reconfigure sprinkler heads for renovation. 

Effect: 
Loss of Fire Protection Water