[159136] in Hotline Meeting
Approved Bldg. 68 - All, Process Hot Water Shutdown
daemon@ATHENA.MIT.EDU (Janine Findlay)
Wed May 30 13:04:37 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "jfucillo@mit.edu" <jfucillo@mit.edu>,
"ckaiser@mit.edu"
<ckaiser@mit.edu>,
"BOBSAUER@MIT.EDU" <BOBSAUER@mit.edu>,
"bbrown@mit.edu"
<bbrown@mit.edu>,
"jmganno@MIT.EDU" <jmganno@mit.edu>,
"jstatile@mit.edu"
<jstatile@mit.edu>,
OPS RM Campus Services East <rm-ecs@mit.edu>,
"Ops
Custodial Admin & Support Staff" <cust-staff@mit.edu>,
"gillooly@MIT.EDU"
<gillooly@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"barnard@mit.edu"
<barnard@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>,
"Ams99@mit.edu"
<Ams99@mit.edu>,
"kasabula@mit.edu" <kasabula@mit.edu>,
"ksimons@mit.edu"
<ksimons@mit.edu>,
"rwong@brighthorizons.com" <rwong@brighthorizons.com>,
"Ops RM Shutdown" <rm-shutdown@mit.edu>,
"cp-command@mit.edu"
<cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>,
Operators
<Operators@plant.mit.edu>,
"DOF Customer Service Center" <dof-csc@mit.edu>,
"Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>,
Ops RM Piping
Systems Team <rm-pipesys@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>
CC: "mmcorrei@mit.edu" <mmcorrei@mit.edu>
Date: Wed, 30 May 2012 13:04:32 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE28A5C74@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved process hot water shutdown for Bldg. 68 - All, on Thursday, May 31, 2012, 12:30pm - 2:30pm, is for your information. Any questions, please contact Mike Correira, x8-9174.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: May 31, 2012
Day: Thursday
Time: 12:30pm - 2:30pm
Building(s): 68
Room(s): All
System: Process Hot Water
Duration: 2 hours
Reason:
to replace a broken steam valve
Effect:
Loss of process hot water for the duration of the shutdown.