[159131] in Hotline Meeting
Approved Bldg. E25 - All, Fire Alarm Shutdown and *Live Audible
daemon@ATHENA.MIT.EDU (Janine Findlay)
Wed May 30 09:43:46 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: Ops RM Fire Protection Team <rm-fire-prot-team@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
Billy Homeyer
<whomeyer@plant.mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Ops Custodial Admin & Support Staff <cust-staff@mit.edu>,
"jdoughty@mit.edu" <jdoughty@mit.edu>, "swade@mit.edu" <swade@mit.edu>,
"bbrown@mit.edu" <bbrown@mit.edu>, "jmganno@MIT.EDU" <jmganno@mit.edu>,
"jstatile@mit.edu" <jstatile@mit.edu>,
"rmarini@mit.edu" <rmarini@mit.edu>,
"colonero@mit.edu" <colonero@mit.edu>,
"kayser@mit.edu" <kayser@mit.edu>, "craigp@MIT.EDU" <craigp@mit.edu>,
OPS RM Campus Services East
<rm-ecs@mit.edu>,
Ops Custodial Admin & Support Staff <cust-staff@mit.edu>,
"srolph@MIT.EDU" <srolph@mit.edu>, "smaram@mit.edu" <smaram@mit.edu>,
"adaz@mit.edu" <adaz@mit.edu>, "jsbanks@mit.edu" <jsbanks@mit.edu>,
"ninadm@mit.edu" <ninadm@mit.edu>, "dgeraci@mit.edu" <dgeraci@mit.edu>,
Michael Smith <masmith@mit.edu>, "willer@mit.edu" <willer@mit.edu>,
"awolpert@mit.edu" <awolpert@mit.edu>,
"brig@med.mit.edu" <brig@med.mit.edu>,
"wayneb@mit.edu" <wayneb@mit.edu>,
MIT Schedules Office <schedules@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"barnard@mit.edu" <barnard@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>,
"bengel@mit.edu" <bengel@mit.edu>, "tquinn@mit.edu" <tquinn@mit.edu>
CC: "biss@mit.edu" <biss@mit.edu>
Date: Wed, 30 May 2012 09:43:42 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE28A5ACF@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved fire alarm shutdown on Thursday, May 31, 2012, 6:00am - 8:00am, and *live audible testing on Friday, June 1, 2012, 6:00am - 8:00am, for Bldg. E25 - All, is for your information. Any questions, please contact Billy Homeyer, x8-0432.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: May 31, 2012
Day: Thursday
Time: 6:00am - 8:00am
Building(s): E25
Room(s): All
System: Fire Alarm and *Live Audible Testing
Duration: 2 hours/day
Reason:
We request bldg E25-all fire alarm shutdowns from 6 AM to 8 AM on Thursday and Friday, May 31st and June 1st, 2012 for MacNichol Electric (Steve MacNichol 781-760-7196) and Simplex (Rich Perron 781-603-7799) to tie-in and program an a/v booth pull station and a closet smoke detector with two associated RAI LED's in classroom E25-117 and to conduct *live audible 3rd party testing of the building E25 fire alarm system from 6 to 8 AM on Friday June 1st*, to be witnessed by J. & M. Brown Co (Wayne Maginnis 617-212-2059, in order to test the new devices and their programming and as part of the E25-111/117 classroom renovation project. Jan Burke 8-5463 and Biss Teelucksingh 2-5972 are the MIT project managers.
Effect:
Loss of fire alarms for the duration of the shutdown and *live audible testing on Friday.