[159108] in Hotline Meeting
Bldg. E18 & E19 Fan Supply AHB-1 #700671 shutdown request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue May 29 09:37:36 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <mcweeney@MIT.EDU>, <alegere@plant.mit.edu>, <shutdowns@MIT.EDU>
Date: Tue, 29 May 2012 09:37:34 -0400
Message-ID: <32AE60B6A99F4F659237CD002E74D756@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Fan Supply AHB1 #700761 shutdown request for Bldg. E18/E19 - Floors 2 & 3, on Friday, June 1, 2012 from7:30am - 11:30am is for your information and response. Any questions, please contact Alan Legere, x3-7636.
Please let us know whether this does or does not have your approval.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0220
Type: Normal
Date: June 1, 2012
Day: Friday
Time: 7:30am - 11:30am
Building(s): E18/E19
Room(s): Floors 2 & 3
System: AHB-1
Duration: 4 hours
Reason:
Annual Preventative Maintenance Inspection.
Effect:
Loss of supply heating/cooling.
This message was sent the following recipients: nsteele@mit.edu; alimart@mit.edu; Swetzel@mit.edu; c_ricci@mit.edu; tswartz@mit.edu; jmganno@MIT.EDU; vang@mit.edu; rm-ecs@mit.edu; mfahie@plant.mit.edu; mobrien@plant.mit.edu; rm-org@mit.edu; adaz@mit.edu; maustin@mit.edu; mcpierce@MIT.EDU; wturner@mit.edu; e19site@mit.edu; opsnote@mit.edu; pconnell@MIT.EDU; annm@mit.edu; heatherg@mit.edu; ejstratt@mit.edu; lab-manager@mit.edu; mscoppa@MIT.EDU; wbarrett@mit.edu; kshikes@MIT.EDU; tquinn@mit.edu;