Approved *Extended - Bldg. E18 and E19 - All, Fire Alarm Shutdown

daemon@ATHENA.MIT.EDU (Janine Findlay)
Fri May 25 14:45:53 2012

From: Janine Findlay <jfindlay@plant.mit.edu>
To: "shutdowns@mit.edu" <shutdowns@mit.edu>,
        Billy Homeyer
	<whomeyer@plant.mit.edu>,
        Ops RM Fire Protection Team
	<rm-fire-prot-team@mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        DOF Customer Service Center
	<dof-csc@mit.edu>,
        Ops Custodial Admin & Support Staff <cust-staff@mit.edu>,
        "nsteele@mit.edu" <nsteele@mit.edu>, "fkg@MIT.EDU" <fkg@mit.edu>,
        "kfjensen@mit.edu" <kfjensen@mit.edu>,
        "alimart@mit.edu" <alimart@mit.edu>,
        "Swetzel@mit.edu" <Swetzel@mit.edu>,
        "wittrup@mit.edu" <wittrup@mit.edu>,
        "gabrieli@mit.edu" <gabrieli@mit.edu>,
        "c_ricci@mit.edu" <c_ricci@mit.edu>, "tej@mit.edu" <tej@mit.edu>,
        "tswartz@mit.edu" <tswartz@mit.edu>, "bbrown@mit.edu" <bbrown@mit.edu>,
        "jmganno@MIT.EDU" <jmganno@mit.edu>,
        "jstatile@mit.edu" <jstatile@mit.edu>, "vang@mit.edu" <vang@mit.edu>,
        "OPS
 RM Campus Services East" <rm-ecs@mit.edu>,
        Michael Fahie
	<mfahie@plant.mit.edu>,
        "Martin O'Brien" <mobrien@plant.mit.edu>, Ops RM All
	<rm-org@mit.edu>,
        "adaz@mit.edu" <adaz@mit.edu>, "maustin@mit.edu"
	<maustin@mit.edu>,
        "dmatthew@mit.edu" <dmatthew@mit.edu>,
        "mcpierce@MIT.EDU"
	<mcpierce@mit.edu>,
        "wturner@mit.edu" <wturner@mit.edu>,
        "e19site@mit.edu"
	<e19site@mit.edu>,
        "opsnote@mit.edu" <opsnote@mit.edu>,
        "segaloff@MIT.EDU"
	<segaloff@mit.edu>,
        "pconnell@MIT.EDU" <pconnell@mit.edu>, "annm@mit.edu"
	<annm@mit.edu>,
        "graposa@MIT.EDU" <graposa@mit.edu>,
        "heatherg@mit.edu"
	<heatherg@mit.edu>,
        "ejstratt@mit.edu" <ejstratt@mit.edu>,
        "lab-manager@mit.edu" <lab-manager@mit.edu>,
        "mscoppa@MIT.EDU"
	<mscoppa@mit.edu>,
        "wbarrett@mit.edu" <wbarrett@mit.edu>,
        "kshikes@MIT.EDU"
	<kshikes@mit.edu>,
        "barnard@mit.edu" <barnard@mit.edu>,
        "monaglek@MIT.EDU"
	<monaglek@mit.edu>,
        "tquinn@mit.edu" <tquinn@mit.edu>
CC: "janb@mit.edu" <janb@mit.edu>
Date: Fri, 25 May 2012 14:45:46 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE28A536D@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following approved *extended fire alarm shutdown on Wednesday, May 23, 2012, 6:00am - 9:00am, and *live audiblet testing on Thursday, May 24, 2012, 6:00am - 9:00am, for Bldg. E18 and E19 - All, *to also include live audible testing on Tuesday, May 29th, 6:00am - 9:00am, is for your information.  Any questions, please contact Billy Homeyer, x8-0432.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381

Type: Normal
Date: May 23, 2012
Day: Wednesday
Time: 6:00am - 9:00am each day
Building(s): E18 and E19
Room(s): All
System: Fire Alarm and *Live Audible Testing
Duration: 3 hours/3 hours
Reason: 
Bennett Communications will be programming in E19 from 6 AM to 9 AM on Wednesday, May 23rd and we will conduct a *live audible 10% test of the bldg E19 fire alarm system from 6 AM to 9 AM on Thursday, May 24th* which will be witnessed by JMBCo.  Billy H. 8-0432.

*Extended - Dear all, I need to extend this bldg E18/E19 fire alarm shutdown in order to complete the 3rd party test of the E19 fire alarm system as related to the new devices and sync module installed for the E19-207 HR office suite and the reprogramming of the three f/a nodes. We will conduct *live audible independent 3rd party 10% testing of the bldg E19 fire alarm system from 6 AM to 9 AM on Tuesday, May 29th *. Thank you, Billy H. 8-0432.


Effect: 
Loss of fire alarms for the duration of the shutdown and *live audible testing on Thursday and Tuesday.
 