[159022] in Hotline Meeting
Rescheduled Bldg. 13-3rd Floor Sprinkler Shutdown Notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu May 24 13:35:38 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <shutdown-response@MIT.EDU>
Date: Thu, 24 May 2012 13:35:31 -0400
Message-ID: <5C7400D4A58A43AC8CDD5AE223EEC44A@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following rescheduled sprinkler, shutdown notification for Bldg. 13-3rd Floor on Tuesday, May 29, 2012 from 6am to 2pm is for your information. No response required to this notification. Any question please contact Billy Homeyer @ 8-0432
We appreciate your patience while the repairs/renovations are in progress.
Thank you
Bill Lombard
Operations Center
Type: Normal
Date: May 29, 2012
Day: Tuesday
Time: 6am
Building(s): 13
Room(s): 3rd Floor
System: Fire Protection Water
Duration: 8 hours
Reason:
Tie-in new sprinkler piping in 13-3044, 3048, and 3064A/B
Effect:
Loss of fire protection water. The Safety Office will be advised of this and notify the Fire Department.