Asbestos Abatement Notification - Bldg. 1, Room 228T

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu May 24 13:11:47 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <gsaffie@MIT.EDU>
Date: Thu, 24 May 2012 13:11:41 -0400
Message-ID: <A3D3892B78794DFAADEFB922E11EBD92@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

This is to notify you of an abatement of approximately 4 linear feet of asbestos containing pipe and valve insulation in Bldg. 1, Room 228T, on Wednesday, June 6, 2012, 7:00am - 4:00pm.  Any questions, please contact Gary Saffie, x2-1796.

We apologize for any inconvenience this may cause you.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381

Type: Normal
Date: June 6, 2012
Day: Wednesday
Time: 7:00am - 4:00pm
Building(s): 1
Room(s): 228T
System: none
Duration: 1 day
Reason: 
Abatement of approximately 4 linear feet of asbestos containing pipe and valve insulation.

Effect: 
There will be no access to this area during the abatement.