Approved - *Revised - Bldg.13-1st floor MBE lab,Fan Supply AHU6,

daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Thu May 24 10:44:44 2012

From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: OPS RM Campus Services Main <rm-mcs@MIT.EDU>,
        "Ops Custodial Admin &
 Support Staff" <cust-staff@MIT.EDU>,
        "jbartels@MIT.EDU" <jbartels@MIT.EDU>,
        "mbulsara@mit.edu" <mbulsara@MIT.EDU>,
        "jeileef@mit.edu" <jeileef@MIT.EDU>, "elk@MIT.EDU" <elk@MIT.EDU>,
        MIT Schedules Office <schedules@MIT.EDU>,
        "jingkong@mit.edu" <jingkong@MIT.EDU>
CC: "shutdowns@mit.edu" <shutdowns@MIT.EDU>,
        "mcweeney@mit.edu"
	<mcweeney@MIT.EDU>,
        Alan Legere <alegere@plant.mit.edu>,
        Ops RM Shutdown
	<rm-shutdown@MIT.EDU>,
        "cp-command@mit.edu" <cp-command@MIT.EDU>,
        "safety@mit.edu" <safety@MIT.EDU>, Operators <Operators@plant.mit.edu>,
        "DOF
 Customer Service Center" <dof-csc@MIT.EDU>
Date: Thu, 24 May 2012 10:44:40 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE28A4D8A@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following Approved Fan Supply AHU 6 and Exhaust Fans EF15, EF16, EF17, EF18 shutdown for Bldg.13-1st flr, MBE lab on Friday, May 25, 2012 is for your information. Any questions, please contact Alan Legere x3-7636.


Thank you,
Bernadette Drinkwater
Repair and Maintenance
X3-0938

Type: Normal
Date: May 25, 2012
Day: Friday
Time: 6:00am - 8:00am
Building(s): Bldg. 13
Room(s): MBE lab 1143, 1143A, 1150, 1155, 1157
System: AHU6 & Fan Exhaust EF15, EF16, EF17, EF18
Duration: 2 hours
Reason: 
Collect mechanical drive information for future overhaul of exhaust fans.

Effect: 
Loss of supply air and exhaust.
 