Bldg.13-1st floor MBE lab,Fan Supply AHU6, Exhaust Fans EF15, EF16, EF17, EF18 shutdown request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed May 23 14:00:13 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <shutdowns@MIT.EDU>, <mcweeney@MIT.EDU>, <alegere@plant.mit.edu>
Date: Wed, 23 May 2012 14:00:11 -0400
Message-ID: <A4F65E75C4B042C5A2490A44C5102866@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Fan Supply AHU 6 and Exhaust Fans EF15, EF16, EF17, EF18 shutdown request for Bldg.13-1st flr, MBE lab on Friday, May 25, 2012 is for your information and response. Any questions, please contact Alan Legere x3-7636.

Would you please let us know whether this does or does not have your approval.

Thank you,
Bernadette Drinkwater
Repair and Maintenance
X3-0938

Type: Normal
Date: May 25, 2012
Day: Friday
Time: 7:30am - 9:30am
Building(s): Bldg. 13
Room(s): MBE lab 1143, 1143A, 1150, 1155, 1157
System: AHU6 & Fan Exhaust EF15, EF16, EF17, EF18
Duration: 2 hours
Reason: 
Collect mechanical drive information for future overhaul of exhaust fans.

Effect: 
Loss of supply air and exhaust.