[158909] in Hotline Meeting
Approved Bldg. NW14 - 2nd Floor (Rooms 2214 - 2218, and 2324),
daemon@ATHENA.MIT.EDU (Janine Findlay)
Mon May 21 14:17:32 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "galanek@mit.edu" <galanek@mit.edu>, "bobk@mit.edu" <bobk@mit.edu>,
"nmorriso@mit.edu" <nmorriso@mit.edu>,
"domara@mit.edu" <domara@mit.edu>, Jack Stark <jstark@plant.mit.edu>,
OPS RM Campus Services West
<rm-wcs@mit.edu>,
"jhaggert@mit.edu" <jhaggert@mit.edu>, "jcrm@MIT.EDU"
<jcrm@mit.edu>,
"pbrenton@MIT.EDU" <pbrenton@mit.edu>,
"censabel@MIT.EDU"
<censabel@mit.edu>,
"mfulton@mit.edu" <mfulton@mit.edu>,
"hrycaj@psfc.mit.edu" <hrycaj@psfc.mit.edu>,
"Ivan@psfc.mit.edu"
<Ivan@psfc.mit.edu>,
"barnard@mit.edu" <barnard@mit.edu>,
"Ops RM Plumbing
Team" <rm-plumbing@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
"Billy
Homeyer" <whomeyer@plant.mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Ops Custodial Admin & Support Staff <cust-staff@mit.edu>
CC: "jcombs@mit.edu" <jcombs@mit.edu>
Date: Mon, 21 May 2012 14:17:29 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE26DB1A8@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved domestic cold water shutdown on Tuesday, May 22, 2012, 6:00am - 9:00am, and fire protection water shutdown notification on Tuesday, May 22, 2012, 6:00am - 12:00pm, for Bldg. NW14 - 2nd Floor (Rooms 2214 - 2218, and 2324), is for your information. Any questions, please contact Billy Homeyer, x8-0432.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: May 22, 2012
Day: Tuesday
Time: 6:00am - 9:00am (Dom. cold Water); 6:00am - 12:00pm (Fire Prot. Water)
Building(s): NW14
Room(s): 2nd Floor (Rooms 2214 - 2218, and 2324)
System: Domestic Cold Water and Fire Protection Water
Duration: 3 hours/6 hours
Reason:
We request a bldg NW14-2nd floor domestic cold water shutdown from 6 AM to 9 AM on Tuesday, May 22nd, 2012 (w/o #5101491) for AHC Mechanical (Guy Fossiano 781-844-7815) to tie-in a 2324 lab safety shower flush line from the 2305 men's room urinal water supply line and an NW14-2nd floor sprinkler shutdown from 6 AM to 12 noon on the same morning (w/o #5101492) to change out the existing sprinkler heads in 2324 to a quick response model as part of the NW14-2324 (and 2214-18) Prof. Ju Li Lab renovation project by MetroWest Construction (Art Alfano 781-706-9705). Jennifer Combs 3-7671 is the MIT project manager.
Effect:
Loss of domestic cold water from 6am - 9am and fire protection water 6am - 12pm.