Bldg. 66 - All (except classroom 110), Air Handlers 1, 2, 3, 4, and 7 Shutdown Request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon May 21 13:12:13 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jcombs@MIT.EDU>
Date: Mon, 21 May 2012 13:12:10 -0400
Message-ID: <AC35EE27CFC24FAE94ED83E981B6EC4D@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following air handlers 1, 2, 3, 4, and 7 shutdown request for Bldg. 66 - All, on Wednesday and Thursday, May 23 and 24, 2012, between 6:00am - 2:00pm (1 to 2 hours each area as listed below), is for your information and response.  Any questions, please contact Billy Homeyer, x8-0432.

Please let us know whether this does or does not have your approval.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381

Type: Normal
Date: May 23, 2012
Day: Wednesday
Time: 6:00am - 2:00pm ( 1 - 2 hours each area)
Building(s): 66
Room(s): All
System: Air Handler 1, 2, 3, 4, and 7
Duration: 1 to 2 hours each area between 6am - 2pm
Reason: 
We request bldg 66-Air hander shutdowns on Wednesday and Thursday, May 23rd and 24th, 2012 as follows; 

on Wed. 5/23 - 
AH3 from 6 to 8 AM, overhead air, offices/classrooms south floors 1 thru 5
AH1 from 8 to 10 AM, overhead air, labs north floors 1 thru 5
AH7 from 10 AM to noon, overhead air basement
AH4 from noon to 2 PM; overhead air sub-basement
on Thurs.5/24 - 
AH2 from 6 to 8 AM, induction units offices/classrooms south floors 1 thru 5
AH3 from 8 to 10 AM, overhead air, offices/classrooms south floors 1 thru 5
AH7 from 10 AM to noon, overhead air basement
AH4 from noon to 2 PM, overhead air sub-basement 

for Shawmut (Dan Cook 617-908-6990) and Ducts Inc. (Darren King 617-908-7370) to conduct another round of fire damper inspections as part of the bldg 66 steam leak recovery project. Jennifer Combs 3-7671 is the MIT project manager.

We will monitor the AH1 space temp sensor in 369 during the AH1 shutdown.


Effect: 
Loss of supply ventilation and cooling air for the duration of the shutdown.