[158830] in Hotline Meeting
Approved Bldg. E23 and E25 - Lab Air and Lab Vacuum, Bldg. E25 -
daemon@ATHENA.MIT.EDU (Janine Findlay)
Fri May 18 13:15:50 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "shutdowns@mit.edu" <shutdowns@mit.edu>,
Ops RM Fire Protection Team
<rm-fire-prot-team@mit.edu>,
Billy Homeyer <whomeyer@plant.mit.edu>,
"Ops RM
Shutdown" <rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
"DOF
Customer Service Center" <dof-csc@mit.edu>,
"Ops Custodial Admin & Support
Staff" <cust-staff@mit.edu>,
"jdoughty@mit.edu" <jdoughty@mit.edu>, "swade@mit.edu" <swade@mit.edu>,
"bbrown@mit.edu" <bbrown@mit.edu>, "jmganno@MIT.EDU" <jmganno@mit.edu>,
"jstatile@mit.edu" <jstatile@mit.edu>,
"rmarini@mit.edu" <rmarini@mit.edu>,
"colonero@mit.edu" <colonero@mit.edu>,
"kayser@mit.edu" <kayser@mit.edu>, "craigp@MIT.EDU" <craigp@mit.edu>,
"OPS
RM Campus Services East" <rm-ecs@mit.edu>,
Ops Custodial Admin & Support
Staff <cust-staff@mit.edu>,
"srolph@MIT.EDU" <srolph@mit.edu>, "smaram@mit.edu" <smaram@mit.edu>,
"adaz@mit.edu" <adaz@mit.edu>, "jsbanks@mit.edu" <jsbanks@mit.edu>,
"ninadm@mit.edu" <ninadm@mit.edu>, "dgeraci@mit.edu" <dgeraci@mit.edu>,
Michael Smith <masmith@mit.edu>, "willer@mit.edu" <willer@mit.edu>,
"awolpert@mit.edu" <awolpert@mit.edu>,
"brig@med.mit.edu" <brig@med.mit.edu>,
"fris@med.mit.edu" <fris@med.mit.edu>,
"sher@med.mit.edu" <sher@med.mit.edu>,
"wayneb@mit.edu" <wayneb@mit.edu>,
MIT
Schedules Office <schedules@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"barnard@mit.edu" <barnard@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>,
"bengel@mit.edu" <bengel@mit.edu>, "tquinn@mit.edu" <tquinn@mit.edu>
CC: "jhimmel@mit.edu" <jhimmel@mit.edu>
Date: Fri, 18 May 2012 13:15:45 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE25B7BF9@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Bldg. E23 and E25 - lab air and lab vacuum and smoke detector and Bldg. E25 - medium pressure steam (autoclaves) shutdown for Saturday, May 19, 2012, 6:00am - 6:00pm, is for your information. Any questions, please contact Billy Homeyer, x8-0432.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: May 19, 2012
Day: Saturday
Time: 6:00am - 6:00pm
Building(s): E23 and E25
Room(s): All
System: Lab Air and Lab Vacuum (E23/E25), Medium Pressure Steam (E25), and Smoke Detectors
Duration: 12 hours
Reason:
We request bldg E23/E25 lab air and lab vacuum shutdowns and an E25 year round medium pressure steam and smoke detectors shutdown from 6 AM to 6 PM on Saturday, May 19th, 2012 for relocating piping in the E25 bsmt construction area to make-way for new ductwork and as part of the E25-AQ's renovation project by Bond Brothers (Andy Cogliano 617-839-8965). Jon Himmel 2-2402 is the MIT project manager.
Note* E25-6th floor HP compressed air not affected
Effect:
Loss of compressed lab air, lab vacuum, medium pressure steam, and smoke detectors for the duration of the shutdown.