Bldg. 5 - All, Heating Hot Water Shutdown Request and Bldg. 5 - Basement, Smoke Detector Shutdown Notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed May 16 13:59:29 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <sinanig@MIT.EDU>
Date: Wed, 16 May 2012 13:59:25 -0400
Message-ID: <398EBC93ADC849B58E97D9432020FAE3@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following heating hot water shutdown request for Bldg. 5 - All, and smoke detector shutdown notification for Bldg. 5 - Basement, on Monday, May 21, 2012, 5:00am - 9:00am, is for your information and response. Any questions, please contact Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: May 21, 2012
Day: Monday
Time: 5:00am - 9:00am
Building(s): 5
Room(s): All
System: Heating Hot Water (All), Smoke Detectors (Basement)
Duration: 4 hours
Reason:
We request a bldg 5-all heating hot water shutdown and a bldg 5-bsmt smoke detector shutdown from 5 AM to 9 AM on Monday, May 21st, 2012 for AHC Mechanical (Guy Fossiano 781-844-7815) to tie-in heating hot water service to three new reheat coils being installed in bsmt labs as part of the project that delivers more supply/make-up air to those labs which are experiencing low air flow and stuffiness. Renovations Inc. (Jim Abbisso 617-594-7650) is the General Contractor and Gerhard Sinani 4-1705 is the MIT project manager.
Effect:
Loss of heating hot water (all) and smoke detectors (basement) for the duration of the shutdown.