[158421] in Hotline Meeting
Appproved - Bldg. 13-All, Fan Supply AH1 #701700 shutdown
daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Thu May 10 13:26:08 2012
From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: OPS RM Campus Services Main <rm-mcs@mit.edu>,
"Ops Custodial Admin &
Support Staff" <cust-staff@mit.edu>,
"jbartels@MIT.EDU" <jbartels@mit.edu>,
"mbulsara@mit.edu" <mbulsara@mit.edu>,
"jeileef@mit.edu" <jeileef@mit.edu>, "elk@MIT.EDU" <elk@mit.edu>,
MIT Schedules Office <schedules@mit.edu>,
"jingkong@mit.edu" <jingkong@mit.edu>
CC: "shutdowns@mit.edu" <shutdowns@mit.edu>,
"whomeyer@mit.edu"
<whomeyer@mit.edu>,
Gary Saffie <gsaffie@plant.mit.edu>,
Alan Legere
<alegere@plant.mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
"DOF
Customer Service Center" <dof-csc@mit.edu>,
Ops RM Shutdown
<rm-shutdown@mit.edu>,
Joseph McWeeney <mcweeney@plant.mit.edu>
Date: Thu, 10 May 2012 13:26:05 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE20086FB@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved shutdown for Bldg. 13-All, Fan Supply AH1 #701700 starting @ 6:00am on Saturday, May 12, 2012 and ending at 9:00am on Sunday, May 13, 2012 is for your information.
Any questions please contact Billy Homeyer x8-0432.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938
We request a Bldg 13-AH1 shutdown from 6 AM on Saturday, May 12th to 9 AM on Sunday, May 13th, 2012 for United Sheet Metal (Fred O'Connor 781-871-1066) to install three reheat coils and associated supply air ductwork in 13-3064 and to allow time for duct sealant to properly cure as part of the NSF funded 13-3064 lab renovation project by Barr and Barr Builders (John Bidgood 508-686-0870). Biss Teelucksingh 2-5972 is the MIT project manager.
Type: Normal
Date: May 12, 2012
Day: Saturday
Time: 6:00am (Sat) - 9:00am (Sun)
Building(s): 13
Room(s): All
System: AH1 #701700
Duration: 27 hours
Reason:
Tie-in reheat coil supply air ductwork and seal it in the lab 13-3064.
Effect:
Loss of ventilation.