Approved - Bldg. E17 AH2 & E18 AH8, AH9, AH10 floors 1- 5 Air

daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Thu May 10 12:35:22 2012

From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: "nsteele@mit.edu" <nsteele@mit.edu>, "c_ricci@mit.edu" <c_ricci@mit.edu>,
        "jmganno@MIT.EDU" <jmganno@mit.edu>, "vang@mit.edu" <vang@mit.edu>,
        "OPS RM
 Campus Services East" <rm-ecs@mit.edu>,
        Ops RM All <rm-org@mit.edu>,
        "Ops
 Custodial Admin & Support Staff" <cust-staff@mit.edu>,
        "heatherg@mit.edu"
	<heatherg@mit.edu>,
        "tquinn@mit.edu" <tquinn@mit.edu>
CC: "shutdowns@mit.edu" <shutdowns@mit.edu>,
        Billy Homeyer
	<whomeyer@plant.mit.edu>,
        Paul Lyons <plyons@plant.mit.edu>,
        Warren Scott
	<WScott@plant.mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        "DOF
 Customer Service Center" <dof-csc@mit.edu>,
        Ops RM Shutdown
	<rm-shutdown@mit.edu>
Date: Thu, 10 May 2012 12:35:18 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE2008696@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following Approved Air Handlers shutdown for Bldg. E17-AH2 & E18-AH8, AH9, AH10 floors 1-5 on Saturday, May 12, 2012 - Monday, May 14, 2012 is for your information. Any questions contact Billy Homeyer x8-0432.

Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938

We request bldg E17-AH2 and E18-AH8, AH9 and AH10 shutdowns from 6 AM on Saturday morning, May 12th to 6 AM on Monday morning, May 14th, 2012 for cutting/capping and sealing supply air trunk runouts serving E17/E18 floors 2 thru 5 and E19 floor 5, (and for allowing an adequate time period for the duct sealant to cure), to make-way for the new design build-out as part of the E17/E18 backfill/Provost's Office swing space project by Barr and Barr Builders (Dick Akins 774-281-0162). Joe Collins 3-3621 and Jan Burke 8-5463 are the MIT project managers.

Type: Normal
Date: May 12, 2012
Day: Saturday
Time: 6:00am (Saturday 5/12) - 6:00am (Monday 5/14)
Building(s): E17/E18
Room(s): Floors 1-5
System: E17 AH2 & E18 AH8, AH9, AH10
Duration: 24 hours
Reason: 
demo/cut/cap and seal supply air truck runouts.

Effect: 
Loss of ventilation/heating/cooling.
 