*Cancelled - *Extended - Approved - Bldg.E18/E19-All, Fire Alarm

daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Thu May 10 11:25:52 2012

From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: "nsteele@mit.edu" <nsteele@mit.edu>, "alimart@mit.edu" <alimart@mit.edu>,
        "Swetzel@mit.edu" <Swetzel@mit.edu>,
        "c_ricci@mit.edu" <c_ricci@mit.edu>,
        "tswartz@mit.edu" <tswartz@mit.edu>,
        "jmganno@MIT.EDU" <jmganno@mit.edu>, "vang@mit.edu" <vang@mit.edu>,
        OPS RM Campus Services East <rm-ecs@mit.edu>,
        Michael Fahie <mfahie@plant.mit.edu>,
        "Martin O'Brien" <mobrien@plant.mit.edu>, Ops RM All <rm-org@mit.edu>,
        "adaz@mit.edu" <adaz@mit.edu>, "maustin@mit.edu"
	<maustin@mit.edu>,
        "mcpierce@MIT.EDU" <mcpierce@mit.edu>,
        "wturner@mit.edu"
	<wturner@mit.edu>,
        "opsnote@mit.edu" <opsnote@mit.edu>,
        "pconnell@MIT.EDU"
	<pconnell@mit.edu>, "annm@mit.edu" <annm@mit.edu>,
        "heatherg@mit.edu"
	<heatherg@mit.edu>,
        "ejstratt@mit.edu" <ejstratt@mit.edu>,
        "lab-manager@mit.edu" <lab-manager@mit.edu>,
        "mscoppa@MIT.EDU"
	<mscoppa@mit.edu>,
        "wbarrett@mit.edu" <wbarrett@mit.edu>,
        "kshikes@MIT.EDU"
	<kshikes@mit.edu>,
        "tquinn@mit.edu" <tquinn@mit.edu>
CC: "shutdowns@mit.edu" <shutdowns@mit.edu>,
        "whomeyer@mit.edu"
	<whomeyer@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        "DOF
 Customer Service Center" <dof-csc@mit.edu>,
        Ops RM Fire Protection Team
	<rm-fire-prot-team@mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>
Date: Thu, 10 May 2012 11:25:44 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE2008603@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The shutdown for Fire Alarm Testing E18/E18-All  has been cancelled for Friday, May 11, 2012.
Thanks for your understanding.

Bernadette Drinkwater
Repair and Maintenance
X3-0938

Dear all, tomorrow's Friday, May 11th E19 fire alarm shutdown for *live audible 3rd party testing* from 6 AM to 9 AM has been cancelled. A decision was made by the project team not to install the required E19-207 suite strobe sync module at this time. The installation, programming and testing for this device will probably not occur now until after Memorial Day. I apologize for any inconvenience or confusion, respectfully, Billy H. 8-0432

Note* we did conduct a brief *live audible acceptance test* in E19 early this morning, Thursday, May 10th.

-----Original Message-----
From: Bernadette Drinkwater 
Sent: Wednesday, May 09, 2012 9:53 AM
To: 'nsteele@mit.edu'; 'alimart@mit.edu'; 'Swetzel@mit.edu'; 'c_ricci@mit.edu'; 'tswartz@mit.edu'; 'jmganno@MIT.EDU'; 'vang@mit.edu'; OPS RM Campus Services East; Michael Fahie; Martin O'Brien; Ops RM All; 'adaz@mit.edu'; 'maustin@mit.edu'; 'mcpierce@MIT.EDU'; 'wturner@mit.edu'; 'opsnote@mit.edu'; 'pconnell@MIT.EDU'; 'annm@mit.edu'; 'heatherg@mit.edu'; 'ejstratt@mit.edu'; 'lab-manager@mit.edu'; 'mscoppa@MIT.EDU'; 'wbarrett@mit.edu'; 'kshikes@MIT.EDU'; 'tquinn@mit.edu'
Cc: 'shutdowns@mit.edu'; 'whomeyer@mit.edu'; cp-command@mit.edu; safety@mit.edu; Operators; DOF Customer Service Center; Ops RM Fire Protection Team; 'rm-shutdown@mit.edu' (rm-shutdown@mit.edu)
Subject: *Extended - Approved - Bldg.E18/E19-All, Fire Alarm Testing w/live audible testing shutdown

This shutdown has been *Extended to include*live audible testing of the Bldg E19 fire alarm system from 6 AM to 9 AM on Friday, May 11th as well as the scheduled testing for tomorrow morning, Thursday, May 10th. Today's, Wednesday, May 9th E19 fire alarm shutdown from 6 AM to 9 AM for programming has been extended to 4 PM also. Any questions please contact Billy Homeyer x8-0432.

Thank you for your understanding.
Bernadette Drinkwater
Repair and Maintenance
X3-0938

Dear all, due to extensive programming required for and associated with the synchronization module being installed for the three new E19-207 office suite speaker/strobes we are required by NFPA to conduct a 100% test of the bldg E19 fire alarm system and therefore I need to extend this shutdown to include *live audible testing of the Bldg E19 fire alarm system from 6 AM to 9 AM on Friday, May 11th as well as the scheduled testing for tomorrow morning, Thursday, May 10th. Today's, Wednesday, May 9th E19 fire alarm shutdown from 6 AM to 9 AM for programming has been extended to 4 PM also. Both the shutdown form and work order 5099320 have been modified to reflect this extension, thank you, Billy H. 8-0432

-----Original Message-----
From: Bernadette Drinkwater 
Sent: Tuesday, May 08, 2012 2:17 PM
To: 'nsteele@mit.edu'; 'alimart@mit.edu'; 'Swetzel@mit.edu'; 'c_ricci@mit.edu'; 'tswartz@mit.edu'; 'jmganno@MIT.EDU'; 'vang@mit.edu'; OPS RM Campus Services East; Michael Fahie; Martin O'Brien; Ops RM All; 'adaz@mit.edu'; 'maustin@mit.edu'; 'mcpierce@MIT.EDU'; 'wturner@mit.edu'; 'opsnote@mit.edu'; 'pconnell@MIT.EDU'; 'annm@mit.edu'; 'heatherg@mit.edu'; 'ejstratt@mit.edu'; 'lab-manager@mit.edu'; 'mscoppa@MIT.EDU'; 'wbarrett@mit.edu'; 'kshikes@MIT.EDU'; 'tquinn@mit.edu'
Cc: shutdowns@mit.edu; whomeyer@mit.edu; cp-command@mit.edu; safety@mit.edu; Operators; DOF Customer Service Center; Ops RM Fire Protection Team
Subject: Approved - Bldg.E18/E19-All, Fire Alarm Testing w/live audible testing shutdown

The following Approved Fire Alarm shutdown for Bldg. E18/E19-All on Wednesday, May 9, 2012 & Thursday, May 10, 2012  with live audible at 6:00am on Thursday, May 10, 2012 is for your information. Any questions please contact Billy Homeyer x8-0432.


Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938

We request bldgs E18 and E19-all fire alarm shutdowns from 6 AM to 9 AM on Wednesday and Thursday, May 9th and 10th, 2012 for McPhee Electric (Mike Doherty 978-852-1354) and Bennett Communications (Mark Popielski 617-799-2614) to tie-in new E19-2nd floor speaker/strobes as follows;

On Wed. 5/9 to deprogram and remove spare audio (2) and visual (2) cards from E18 bsmt and 4th floor autocall panels and install and program them into the E19 bsmt panel, tie-in 3 new E19-207 suite speaker strobes and tie-in/program one sync module;

On Thurs. 5/10 to conduct *live audible NFPA acceptance testing* in E18/E19 and conduct *live audible independent 3rd party testing of the E19 fire alarm system*, to be witnessed by JMBCo (Wayne Maginnis 617-212-2059), to test the one relocated elevator lobby a/v and the three new a/v's installed in the HR suite and as part of the E17/E18 backfill project by Barr and Barr (Dick Akins 774-281-0462). Jan Burke 8-5463 and Joe Collins 3-3621 are the MIT project managers.



Type: Normal
Date: May 9, 2012
Day: Wednesday
Time: 6:00am - 9:00am
Building(s): E18/E19
Room(s): All
System: Fire Alarm system
Duration: 3 hours each day
Reason: 
Tie - in program, *live test* 3 new, 1 relocated a/v's and 1 sync module for E19-207.

Effect: 
Fire Alarm and live audible testing. 