[158139] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 76 - Air Handle AH1 -AH10 shutdown request

daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Mon May 7 09:05:42 2012

From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: "myersm@MIT.EDU" <myersm@mit.edu>, "jmganno@MIT.EDU" <jmganno@mit.edu>,
        OPS RM Campus Services East <rm-ecs@mit.edu>,
        "abhughes@mit.edu"
	<abhughes@mit.edu>,
        "tjacks@mit.edu" <tjacks@mit.edu>,
        "cquense@mit.edu"
	<cquense@mit.edu>,
        "cjbeal@mit.edu" <cjbeal@mit.edu>,
        "rlanger@MIT.EDU"
	<rlanger@mit.edu>,
        "Ifmoura@mit.edu" <Ifmoura@mit.edu>
CC: "whomeyer@mit.edu" <whomeyer@mit.edu>,
        "shutdowns@mit.edu"
	<shutdowns@mit.edu>,
        Paul Lyons <plyons@plant.mit.edu>,
        Warren Scott
	<WScott@plant.mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>
Date: Mon, 7 May 2012 09:05:39 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE12886F7@dof-exchmbx01.facilities.ms.mit.edu>
In-Reply-To: <6A848B685CCF4D429C89A04AE9198CD2@facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following Air Handler AH1 - AH10 shutdown request for Bldg. 76 starting May 14, 2012 - Tuesday, May 22, 2012 is for your information and response.  Please see schedule below. Please contact Billy Homeyer with any questions. No effect; other fans will ramp up to maintain capacity.

Thank you,
Bernadette Drinkwater
Repair and Maintenance
X3-0938

We request bldg 76-AH1 thru AH10 shutdowns for DAC Sales (Steve Shelley 617-803-8206) to install duct sealant around air handling unit cooling coil frames to prevent moisture and excessive condensation within these fan sections as follows;

AH1 and AH10 from 6 AM on Monday, May 14th to 6 AM on Tuesday, May 15th;

AH2 and AH9 from 6 AM on Tuesday, May 15th to 6 AM on Wednesday, May 16th;

AH3 and AH8 from 6 AM on Wednesday, May 16th to 6 AM on Thursday, May17th;

AH4 and AH5-AQ's from 6 AM on Thursday, May 17th to 6 AM on Friday, May 18th;

AH7 from 6 AM on Friday, May 18th to 6 AM on Monday, May 21st;

AH6-AQ's from 6 AM on Monday, May 21st to 6 AM on Tuesday, May 22nd, 2012;

and all as part of the KOCH Institute building project. Marty Deluga 4-5081 is the MIT project manager.


Type: Normal
Date: May 14, 2012
Day: Monday
Time: 6:00am 
Building(s): 76
Room(s): See Schedule
System: See Schedule
Duration: 24 hrs each day ex AH7
Reason: 
Apply duct sealent around coil coil frames to reduce moisture and condensate

Effect: 
Loss of ventilation. No effect; other fans will ramp up to maintain capacity.




home help back first fref pref prev next nref lref last post