[158068] in Hotline Meeting
Update - Emergency Shutdown - Bldg. 18 - ALl RO/DI water shutdown
daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Fri May 4 08:34:22 2012
From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: "jdoughty@mit.edu" <jdoughty@mit.edu>, "swade@mit.edu" <swade@mit.edu>,
"rjwilk@mit.edu" <rjwilk@mit.edu>,
OPS RM Campus Services East
<rm-ecs@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>
CC: Paul Lyons <plyons@plant.mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>,
MIT Schedules Office <schedules@mit.edu>,
"Ops
Custodial Admin & Support Staff" <cust-staff@mit.edu>,
Ops RM Shutdown
<rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Warren Scott <WScott@plant.mit.edu>,
Operators
<Operators@plant.mit.edu>
Date: Fri, 4 May 2012 08:34:19 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE12881EC@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The RO/DI water for Bldg. 18-All has been repaired.
Thank you for your patience.
Bernadette Drinkwater
Repair and Maintenance
X3-0938
-----Original Message-----
From: shutdown-response@MIT.EDU [mailto:shutdown-response@MIT.EDU]
Sent: Thursday, May 03, 2012 1:14 PM
To: undisclosed_recipients@mit.edu
Cc: Paul Lyons; shutdowns@mit.edu; MIT Schedules Office; Ops Custodial Admin & Support Staff; Ops RM Shutdown; cp-command@mit.edu; safety@mit.edu; Operators; DOF Customer Service Center
Subject: Emergency Shutdown - Bldg. 18 - ALl RO/DI water shutdown
Importance: High
The following Emergency RO/DI water shutdown notification for Bldg. 18-All, on Thursday, May 3, 2012, 1:15pm - until repairs are complete, is for your information. Any questions, please contact Paul Lyons, x3-5721.
We apologize for any inconvenience this may cause.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938
Type: Normal
Date: May 3, 2012
Day: Thursday
Time: 1:15pm - until repairs are complete
Building(s): 18
Room(s): All
System: RO/DI water
Duration: until repair are complete
Reason:
emergencies repairs need to be made to a bad leak on the RO/DI system.
Effect:
Loss of RO/DI water for the duration of the shutdown.
This message was sent the following recipients: jdoughty@mit.edu; swade@mit.edu; rjwilk@mit.edu; rm-ecs@mit.edu; heatherg@mit.edu;