[157960] in Hotline Meeting
Bldg. 13 - 3rd Floor, Heating Hot Water Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue May 1 12:43:03 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <biss@MIT.EDU>
Date: Tue, 1 May 2012 12:43:00 -0400
Message-ID: <7870D95B902042458B4D836367C2F173@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following heating hot water shutdown request for Bldg. 13 - 3rd Floor, on Tuesday, May 8, 2012, 6:00am - 10:00am, is for your information and response. Any questions, please contact Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: May 8, 2012
Day: Tuesday
Time: 6:00am - 10:00am
Building(s): 13
Room(s): 3rd Floor
System: Heating Hot Water
Duration: 4 hours
Reason:
We request a bldg 13-3rd floor heating hot water shutdown (hhw to interior FCU's and reheat coils; the CV5 PMP11 system; perimeter induction units hhw is not affected)) from 6 AM to 10 AM on Tuesday, May 8th, 2012 for J C Cannistraro Mechanical (Jim AcAleer 617-293-4542) to tie-in 3 new reheat coils being installed in 13-3064 as part of the NSF funded project for this lab space by Barr and Barr Builders (John Bidgood 508-686-0870). Biss Teelucksingh 2-5972 is the MIT project manager.
Effect:
Loss of heating hot water and supply heating air for the duration of the shutdown. Perimeter induction units heating hot water is not affected.