Bldg. N51 and N52 - All, Fire Alarm Shutdown Notification and *Live Audible Testing Request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Apr 30 09:52:57 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <koskae@MIT.EDU>
Date: Mon, 30 Apr 2012 09:52:52 -0400
Message-ID: <ED0E38799977450A804BFAD2EB97006B@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following fire alarm shutdown notification for Tuesday, May 1, 2012, 7:30am - 2:30pm, Wednesday, May 2, 2012, 6:00am - 2:00pm, and Thursday and Friday, May 3 & 4, 2012, 6:00am - 9:00am each day, and a *live audible testing request for Wednesday, Thursday and Friday, May 2, 3 & 4, 2012, 6:00am - 9:00am each day, for Bldg. N51 and N52 - All, is for your information and response.  Any questions, please contact Billy Homeyer, x8-0432.

Please let us know whether this does or does not have your approval.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381

Type: Normal
Date: May 1, 2012
Day: Tuesday
Time: 7:30am - 2:30pm (5/1); 6:00am - 2:00pm (5/2); 6:00am - 9:00am (5/3 & 5/4)
Building(s): N51 and N52
Room(s): All
System: Fire Alarm and *Live Audible Testing
Duration: 7 hours/8 hours/3 hours/3 hours
Reason: 
We request bldg N51/N52 fire alarm shutdowns on Tuesday, May 1st through
Friday, May 4th, 2012 as follows; 

from 7:30 AM to 2:30 PM on Tues 5/1 for McPhee Electric (Michael Moore 781-393-7993)/Simplex (Rich Perron 781-603-7799) to tie-in and program new N51-3rd fl fire alarm devices (a/v's, pulls, smokes, tamper and w/f's); 

and from 6 AM to 9 AM on Wed/Thurs/Fri 5/2,3,4 to conduct *live audible testing of the bldg N51/N52 fire alarm system* - NFPA required acceptance testing on Wed 5/2, 1st party testing on Thurs 5/3 and 3rd party testing on Fri 5/4. 3rd party testing will be witnessed by J. & M. Brown Co (Wayne Maginnis 617-212-2059); 

and all as part of the N51-3rd floor Doc Edgerton lab relocation project by Bond Brothers (Steve Goodwin 617-212-0438/Patrick Joyce 617-895-6741). Evan Koska 4-6173 and Biss Teelucksingh 2-5972 are the MIT project managers.

Please note that the shutdown for Wednesday, May 2nd is extended, following live testing, until 2 PM for additional programming per the outcome of the initial acceptance test.

Tues 5/1 at 7:30 AM; MIT Fire, Bond, McPhee, Simplex (confirmed), JMBCO (1)
Wed 5/2 at 6 AM; MIT Fire, MIT Sprinkler, Bond, McPhee, Simplex (confirmed), JMBCO (1)
Thurs 5/3 at 6 AM; MIT Fire, Bond, McPhee, Simplex (if necessary), JMBCO (1)
Fri 5/4 at 6 AM; MIT Fire, MIT Sprinkler, Bond, McPhee, JMBCo (2) 




Effect: 
Loss of fire alarms for the duration of the shutdown and *live audible testing on Wednesday, Thursday, and Friday.