Bldg. 26 - All, Fire Alarm Shutdown Notification and *Live Audible Testing Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri Apr 27 10:05:04 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jcombs@MIT.EDU>
Date: Fri, 27 Apr 2012 10:04:38 -0400
Message-ID: <67DE32187B4E41AFBE8CD35EB58482E0@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following fire alarm shutdown notification for Monday, April 30, 2012, 1:00pm - 3:00pm and Tuesday, May 1, 2012, 6:00am - 7:00am, with a *live audible testing request for Tuesday, May 1, 2012, 6:00am - 7:00am, is for your information and request. Any questions, please contact Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: April 30, 2012
Day: Monday
Time: 1:00pm - 3:00pm (4/30) and 6:00am - 7:00am (5/1)
Building(s): 26
Room(s): All
System: Fire Alarm and *Live Audible Testing
Duration: 2 hours/1 hour
Reason:
We request bldg 26-all fire alarm shutdowns on Monday and Tuesday, April 30th and May 1st, 2012 as follows; from 1 PM to 3 PM on Mon 5/1 for Fire Command Systems (tech is Andy, contact is Ara Bernstein 978-473-9964) to install a 26-041 oxygen sensor relay to report to the fire alarm system from the building management system; and from 6 AM to 7 AM on Tues 5/1 to conduct a brief *live audible 3rd party test of the building fire alarm system*, to be witnessed by J. & M. Brown Co. (Wayne Maginnis 617-212-2059), to clear the last remaining fire alarm punchlist item as part of the 26-041 MRI Lab project by Wise Construction (Chris Luongo 781-389-5749). Jennifer Combs 3-7671 and Varin Ang 4-2243 are the MIT project managers.
Effect:
Loss of fire alarms for the duration of the shutdown and *live audible testing on Tuesday.