[157803] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Approved Bldg. 1,2,3,4,5,6,7,7A,8,10, & 11 - All, Emergency Building Power Shutdown

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Apr 26 13:08:15 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <pisanin@MIT.EDU>
Date: Thu, 26 Apr 2012 13:07:55 -0400
Message-ID: <6CAEA4E640114020931B1E20C07C1155@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following approved building power (emergency power only) shutdown for Bldg. 1,2,3,4,5,6,7,7A,8,10, & 11 - All, on Friday, April 27, 2012, 12:01am - 6:30am, is for your information.  Any questions, please contact Nicole Pisani, x5-5157.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381


Type: Normal
Date: April 27, 2012
Day: Friday
Time: 12:01am - 6:30am
Building(s): 1,2,3,4,5,6,7,7A,8,10, & 11
Room(s): All
System: Building Power (Emergency Power only)
Duration: 6.5 hours
Reason: 
We request a Building 10 Normal Emergency Power shutdown, all Buildings 1,2,3,4,5,6,7,7A,8,10,11 emergency power from 12:01am until 6:30am on Friday April 27th for Broadway Electric (Bob Leblond 617-908-8550) to install and tie in a new electrical feed as part of the Building 3- ECM normal emergency power upgrade project by O'Connor Constructors (Paul Daley 617-828-7765). Nicole Pisani 5-5157 and Joe Collins 3-3621 are the MIT project managers.

This will involve all emergency power and elevator service in the buildings listed above. Elevators in Buildings 9, 16, 24, and 26 will be available to use during this shutdown timeframe to access the main group. ** Per discussions with the Information Services & Technology Department there will be no network (wireless and hard wired) and Voip service only in the following areas: 
-Building 4 -All of basement except near 065 -Building 4-1st  floor from rooms 104-145 -Building 10 -4th floor all -Building 10- 5th floor all -Building 11 -1st floor all -Building 11 -3rd floor all**

If there are any questions please contact Nicole Pisani x 5-5157


Effect: 
Loss of elevators in these buildings (elevators will be operational in Bldg. 9, 16, 24, and 26) and emergency building power for the duration of the shutdown.  Please see additional effects above.