> Bill from Physical Plant called about the scheduled shutdown in
building 13 (including room 13-3064) which will occur from Sunday the
22nd at 11pm to Monday 2am. There will be no ventilation.
>
Subject: Building 36
Bill from physical plant called about a scheduled shutdown in building
36 on Monday the 23rd, 1 to 2am. It's for electrical PM work and will
affect floors 2 through 8
Subject: Building 18
Thursday Nov. 19, 12-2 am, no ventilation on south side of building.
Subject: Building 18
Friday Nov. 20, 12-2 am, no ventilation on north side of building.
Subject: Building 39
Sunday 11-29 11pm to Monday 11-30 3am recirculating fans for 299A & 428.
Subject: Building 39
Thursday Dec. 3, 12-7 am, supply fans for electrical PM work, 2 hr each.