Mary Files (3-1500) called and reported to Sue that there
was going to be an emergency shutdown of power in E52 on 
the 1st 2nd & 3rd floor.  But that it would not effect 
lights or recepticals, this didn't make sense so called 
and found out that it will effect everything.  So be 
prepared for computer problems and net problems.

Should only take 1/2hr to complete work.

JJ

Work has been completed for now.  Problem was with power
panel in E52-364 (yes there is a dept cluster in there),
and we should be all proud of our equip, it all came back
up with no problems.

Don Haze was electrical super on site.  A backup circuit
breaker is going to be ordered and electricians are going
to be keeping an eye on it.

So for now problem solved and case closed.

JJ