[500] in I/T Delivery
Enterprise Backup Monthly Report
daemon@ATHENA.MIT.EDU (Grant Young)
Wed Jun 6 15:38:19 2001
Message-Id: <4.3.2.7.2.20010606153647.03738750@po12.mit.edu>
Date: Wed, 06 Jun 2001 15:37:42 -0400
To: delivery@mit.edu
From: Grant Young <gyoung@MIT.EDU>
Cc: ebs-l@mit.edu, kelley@mit.edu, rar@mit.edu
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"; format=flowed
Project Name: Enterprise Backup System
Project Leader: Grant Young
Report Date: June 6, 2001
URL: http://windsurf.mit.edu/ebs
Issues:
* Setting up the infrastructure for online backups is taking longer that
expected due to disk space and other resource limitations.
Accomplishments Past Period:
* Continued maintence and operation of the E40 systems.
* Created draft consolidated reports for daily backup success and
failure. One set for general backups and another for the SAP online backups.
* Started reconfiguration of the SAN in W91 to support NetBackup.
Goals for the Coming Period
* Finish re-configuring SAN in W91 to support Netbackup. In particular
moving the tape drives on the Tape Library onto the SAN
* Installing the NetBackup software and activating the W91 Master Server.
* Rolling out online backups fully on at least one host in E40.
* Putting the draft backup reports on the web.
* Investigate using a database to facilitate reporting.
* Updating the Team's web pages.
Team Dynamics:
* Good.
Lessons Learned:
* Rome wasn't built in a day.
----------------
Grant Young, MIT Information Systems
Administrative Servers Service Team
W91-219B -- 253-7529