Project Name: MIT Events Calendar
Project Leader: Stephen Turner
Report Date: December 4, 2000 
Submitted by: Stephen Turner
URL: http://web.mit.edu/is/delivery/eventscalendar/

This Month's Accomplishments

* The "1.2" enhancements were completed and released as planned on
  Monday November 27.
* Usability team aided in testing the new features.
* All affected users were notified in advance of upcoming changes
  to the system.
* 2 quick-start style demos of the enhanced calendar were scheduled to
  take place in December.

Next Month's Plans

* 2 quick-start style demos of the enhanced calendar.
* Begin planning for the "1.5" enhancements.

Issues

* The 1.2 release represents a significant milestone for this project.
  The enhancements have been made in response to the constructive
  comments and suggestions we have received since the May 2000 release
  of the events calendar. The process will continue with the next stage,
  release 1.5 sometime early next year.