[391] in I/T Delivery
EBS Monthly Delivery Report
daemon@ATHENA.MIT.EDU (Rachel Sage)
Thu Nov 30 16:30:06 2000
Message-Id: <10011302131.AA20337@MIT.EDU>
Date: Thu, 30 Nov 00 16:27:48 EST
From: Rachel Sage <SAGE@MITVMA.MIT.Edu>
To: delivery@MIT.EDU
Cc: Peter B Kelley <KELLEY@MIT.EDU>, Roger A Roach <RAR@MIT.EDU>,
ebs-l@MIT.EDU
Project Name: Enterprise Backup System
Project Leader: Rachel Sage
Report Date: November 30, 2000
URL: http://windsurf.mit.edu/ebs
Issues:
* The current project lead, Rachel Sage, is leaving IS and Grant Young,
a current member EBS team member, will be taking over as project lead as
of December 1.
* The month of November has mostly been spent on two items; tracking
down a major tape handling bug within the NetBackup product and
adjusting to the departure of the project lead.
In particular, the tape handling bug caused us to miss a number of
backups in a row. We've had to stop progress in other areas of the
project in order to fix the problem and regain enough confidence in
the product to move forward again.
* We are continuing to run up against the SAP 4.6c upgrade with respect
to resource and system availability.
Accomplishments Past Period:
* Created work around for major tape handling bug.
* Appointed new project lead
* Transferred project plan, knowledge, and responsibilities to the new
project lead.
Goals for the Coming Period
* Break in new project lead.
* Determine requirements and dates for rollout of online db backups
in E40.
* Determine requirements for rollouts in W91.
Team Dynamics:
* Obviously, the team is going to need some time to adjust to the
change in project leadership and the reduction in project resources.