[316] in I/T Delivery
SAP Data Archiving Pilot - Monthly Report
daemon@ATHENA.MIT.EDU (Sebastien Sabre)
Fri Jul 7 09:16:05 2000
Message-Id: <200007071316.JAA10693@melbourne-city-street.MIT.EDU>
Date: Fri, 07 Jul 2000 09:17:48 -0400
To: delivery@mit.edu
From: Sebastien Sabre <ssabre@MIT.EDU>
Cc: huxley@mit.edu
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"
Project Name: SAP Data Archiving Pilot
Project Leader: Bil Huxley, Sebastien Sabre
Report Date: 7/7/2000
Submitted by: Sebastien Sabre
Accomplishments Past Period:
----------------------------
* Started project pre-planning
- Project motivation
- Resource plan
- List of project deliverables
- Preliminary work breakdown structure for pilot
* Held critical meeting with sponsors and key stakeholders
* Held meeting with FSS team leaders.
* Projected database growth for the next 18 months
* Identified large and fast-growing DB tables
* Selected archiving objects candidate for the archiving pilot ("Low
hanging fruits")
Goals for the Coming Period:
----------------------------
* Complete project pre-planning
- Communication plan / Project notebook
* Take delivery of SAP environment for pilot
* Start pilot
* Meet with sponsors
* Follow-up with FSS
Issues:
-------
* Competition for resources with the SAP 4.6C upgrade + potential timeline
conflicts.
* Depending on the objects chosen for the Pilot, reaching consensus on the
business requirements and putting together thorough test plans could be
challenging, particularly this time of year.
Additional Comments:
--------------------