Re: Battery Maint in LEC equipment

daemon@ATHENA.MIT.EDU (Michael Loftis)
Tue Jun 7 22:05:55 2005

Date: Tue, 07 Jun 2005 20:05:23 -0600
From: Michael Loftis <mloftis@wgops.com>
To: nanog@nanog.org
In-Reply-To: <Pine.LNX.4.58.0506052006210.14555@ohtf.fo.jrfg.arg>
X-MailScanner-From: mloftis@wgops.com
Errors-To: owner-nanog@merit.edu




--On June 5, 2005 8:11:41 PM -0700 Jay Hennigan <jay@west.net> wrote:


> The corollary to this question:
>
> If your data center has an adequate DC plant, will the carriers insist
> on installing their own batteries and rectifiers?  And how many of them
> have redundant supplies to take advantage of an A and B feed from you?

There's no typical response.  Here in QWest territory they drop their own 
cabinet and pull AC power for their own rectifiers and battery string 
inside the cabinet.  (I helped lump the freaking batteries oy...)

--
"Genius might be described as a supreme capacity for getting its possessors
into trouble of all kinds."