[81323] in North American Network Operators' Group

home help back first fref pref prev next nref lref last post

Re: Battery Maint in LEC equipment

daemon@ATHENA.MIT.EDU (Chris Adams)
Sat Jun 4 14:10:07 2005

Date: Sat, 4 Jun 2005 13:09:40 -0500
From: Chris Adams <cmadams@hiwaay.net>
To: nanog list <nanog@merit.edu>
Mail-Followup-To: Chris Adams <cmadams@hiwaay.net>,
	nanog list <nanog@merit.edu>
In-Reply-To: <200506041454.KAA06700@sigma.nrk.com>
Errors-To: owner-nanog@merit.edu


Once upon a time, David Lesher <wb8foz@nrk.com> said:
> Have any NANOG'ers [NANOGites? NANOGees?] run into this? Again, this
> is LEC owned, LEC maintained, equipment....Do you provide generator
> power for such in your space?

We do provide generator power in our space to the telcos.  BellSouth has
a big (pre-existing) battery bank, but KMC didn't install batteries
(there wasn't much point; if our UPS and generator fail, there's nothing
for them to provide service to).

In this area, I believe that BellSouth uses natural gas powered
generators, as many of the remote cabinets (installed in the last 5-7
years or so anyway) have a gas meter next to them and a line running
into a second cabinet (generator/power supply I suppose).

-- 
Chris Adams <cmadams@hiwaay.net>
Systems and Network Administrator - HiWAAY Internet Services
I don't speak for anybody but myself - that's enough trouble.

home help back first fref pref prev next nref lref last post