Re: Re[2]: telehouse - 25 broadway

daemon@ATHENA.MIT.EDU (mike harrison)
Sun Sep 16 17:59:09 2001

Date: Sun, 16 Sep 2001 17:58:26 -0400 (EDT)
From: mike harrison <meuon@highertech.net>
To: Gwendolynn ferch Elydyr <gwen@reptiles.org>
Cc: Brian Whalen <bri@sonicboom.org>,
	Sean Donelan <sean@donelan.com>, "nanog@merit.edu" <nanog@merit.edu>
In-Reply-To: <Pine.BSF.4.33.0109161723100.64949-100000@iguana.reptiles.org>
Message-ID: <Pine.LNX.4.10.10109161749220.7056-100000@home.highertech.net>
MIME-Version: 1.0
Content-Type: TEXT/PLAIN; charset=US-ASCII
Errors-To: owner-nanog-outgoing@merit.edu


> How many folks actually perform a load transfer to the generator during
> testing to check out the transfer switch ?

Back in my military hospital days, we did both regular load tests,  
using a LARGE resistive loads we flowed water through to cool (4" feed
pipe) as well did actual swapovers (on weekends).

Never seen it done that way since, when we bought our current generator
system the company that installed it thought I was crazy for even asking
about a test load. 

We do do a full swapover every few months... --Mike--