[22363] in North American Network Operators' Group

home help back first fref pref prev next nref lref last post

Re: OUTAGE: DACS failure in USWEST/spokane

daemon@ATHENA.MIT.EDU (David Lesher)
Sun Dec 27 10:20:33 1998

From: David Lesher <wb8foz@nrk.com>
To: nanog@merit.edu (nanog list)
Date: Sun, 27 Dec 1998 10:09:52 -0500 (EST)
In-Reply-To: <981227083801.21b12@SDG.DRA.COM> from "Sean Donelan" at Dec 27, 98 08:38:01 am

Unnamed Administration sources reported that Sean Donelan said:
> 
> Now the story starts changing.  The telco is now saying it was
> a power outage, and the standby power failed at the central
> office.

I have often wondered how vigilant of late the LEC's are in
maintaining their standby power systems. It takes manpower & money
to keep on top of same [In general, it should be run under some
load for an hour, and that should be done once a ~week/month.].
Seeing as how they can't keep other slots filled....

Further, at one time the spec called for the battery plant to
last long enough for a truck-mounted generator to get there when
the in-place unit bits the onion. Wonder if that is still true....


-- 
A host is a host from coast to coast.................wb8foz@nrk.com
& no one will talk to a host that's close........[v].(301) 56-LINUX
Unless the host (that isn't close).........................pob 1433
is busy, hung or dead....................................20915-1433

home help back first fref pref prev next nref lref last post