On Wed, 23 Jul 2014, Scott Helms wrote:
> They are also running into serious problems trying to scale and while
> getting 400 homes wired up is laudable, having it take more than two years
> is not impressive at all.
I am impressed by it. 200km of fiber is not easy to do.
--