>> concrete roadway, just packed earth and rock? Environmental limitations do
>>
>
> My best guess is that you would want to use directional boring in that case. A
> small hole every couple hundred meters, horizontal bore and duct pullback
You'll struggle to get a directional drill through material that
includes rock.
It's two days work for this kit
http://www.youtube.com/watch?v=acTBl8UKNaQ