[119034] in North American Network Operators' Group

home help back first fref pref prev next nref lref last post

Re: HE.net, Fremont-2 outage?

daemon@ATHENA.MIT.EDU (Scott Howard)
Wed Nov 4 22:51:25 2009

In-Reply-To: <1257388693.973329082@192.168.1.71>
Date: Wed, 4 Nov 2009 19:50:19 -0800
From: Scott Howard <scott@doc.net.au>
To: nevin@enginehosting.com
Cc: nanog@nanog.org
Errors-To: nanog-bounces+nanog.discuss=bloom-picayune.mit.edu@nanog.org

On Wed, Nov 4, 2009 at 6:38 PM, <nevin@enginehosting.com> wrote:

> The 2002 press release is talking about the Fremont 1 facility not the
> newer Fremont 2 facility.  Fremont 1 has a fixed power availability to each
> cabinet of just a single 15A circuit.  You can not modify or change that,
> and if you need more power your option is to add another cabinet. You are
> not allowed to route power cords between cabinets so you are forever running
> a single circuit and 80% of your 15A circuit max.  The data center was built
> in a different time.
>

A different time, but obviously not that much different...

Fremont 2 is still limited to either a single 15A or a single 20A circuit
per rack.

They are rebuilding one of the Fremont 2 wings and turning it into a single
area rather than the existing suites, so it'll be interesting to see if
things are done differently there.

  Scott