We are in the process of evaluating Equinix and CRG West in LA. Before =
we ink a deal, can anyone give some feedback on CRG West? I have had =
some minor direct operational experience with them in the past with a =
former employer. If anyone has some history with them; good, bad or =
informational on things to watch for throughout a lifecycle of a couple =
years with them would be appreciated. They seem pretty sound, but some =
things have cropped up as we have started looking at a possible =
contract.=20
So if you have an opinion on the following please let me know on/off =
list as appropriate:
Difficulties during contract phase other than terms. i.e. rights =
assignments, reps and warrants, etc..
Implementation issues during setup and install.
Operational issues with HVAC/power/xcons/remote hands..
Any2 pitfalls.
Integrity if issues arise.
Comments would be welcome.. thanks!