[115155] in North American Network Operators' Group

home help back first fref pref prev next nref lref last post

Data Centers in LA - CRG West

daemon@ATHENA.MIT.EDU (Flint E. Barber)
Thu Jun 11 00:02:13 2009

Date: Wed, 10 Jun 2009 22:01:59 -0600
From: "Flint E. Barber" <flintbarber@flintrock.com>
To: <nanog@nanog.org>
Errors-To: nanog-bounces+nanog.discuss=bloom-picayune.mit.edu@nanog.org


We are in the process of evaluating Equinix and CRG West in LA. Before =
we ink a deal, can anyone give some feedback on CRG West? I have had =
some minor direct operational experience with them in the past with a =
former employer. If anyone has some history with them; good, bad or =
informational on things to watch for throughout a lifecycle of a couple =
years with them would be appreciated. They seem pretty sound, but some =
things have cropped up as we have started looking at a possible =
contract.=20

So if you have an opinion on the following please let me know on/off =
list as appropriate:

 Difficulties during contract phase other than terms. i.e. rights =
assignments, reps and warrants, etc..
 Implementation issues during setup and install.
 Operational issues with HVAC/power/xcons/remote hands..
 Any2 pitfalls.
 Integrity if issues arise.

Comments would be welcome.. thanks!

Regards,
-Flint

home help back first fref pref prev next nref lref last post