Re: Steps/Process for a Patch release

daemon@ATHENA.MIT.EDU (Matt Braun)
Thu Oct 28 12:14:46 1993

To: tjm@MIT.EDU (Tim McGovern)
Cc: release-76@MIT.EDU, op@MIT.EDU, rel-eng@MIT.EDU, acmg@MIT.EDU,
In-Reply-To: Your message of Thu, 28 Oct 93 11:31:04 -0500.
Date: Thu, 28 Oct 93 12:13:57 EDT
From: Matt Braun <mhbraun@MIT.EDU>


Is it necessary to have 3 messages to athena-outage for each fix ?
Athena-outage has recently been fairly low traffic, and sending constant
status reports to it might diminish its impact when other outages are
announced.


I would recommend having the mail to athena-outage that says when the fix will
be in the field give a time frame and only send out a followup if that time
frame is not met.