[2463] in Release_Engineering
7.2 Schedule
daemon@ATHENA.MIT.EDU (Richard Basch)
Tue Oct 9 15:07:53 1990
Date: Tue, 9 Oct 90 15:07:35 -0400
To: release@MIT.EDU, release72@MIT.EDU
Cc: rel-eng@MIT.EDU
From: Richard Basch <probe@MIT.EDU>
After a discussion with Ezra and Peter, the following timeline was
formed:
Fri Nov. 16 code cut
Mon Dec. 10 "Friendly test" begins
Mon Jan. 07 "Staff test" begins
Mon Jan. 28 Official hand-off to Operations
Wed Jan. 30 Release hits the field
Fri Feb. 1 Second-term classes begin
-Richard