7.2 Schedule

daemon@ATHENA.MIT.EDU (Richard Basch)
Tue Oct 9 15:07:53 1990

Date: Tue, 9 Oct 90 15:07:35 -0400
To: release@MIT.EDU, release72@MIT.EDU
Cc: rel-eng@MIT.EDU
From: Richard Basch <probe@MIT.EDU>


After a discussion with Ezra and Peter, the following timeline was
formed:

	Fri Nov. 16	code cut
	Mon Dec. 10	"Friendly test" begins
	Mon Jan. 07	"Staff test" begins
	Mon Jan. 28	Official hand-off to Operations
	Wed Jan. 30	Release hits the field

	Fri Feb. 1	Second-term classes begin

-Richard