[77219] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Re: Bldg. 38 - Air Handler 3/Supply Fans 3A and 3B Preventive

daemon@ATHENA.MIT.EDU (Elizabeth D Cooper)
Tue May 18 13:34:12 2004

Message-Id: <5.2.1.1.2.20040518132647.02e344d8@hesiod>
Date: Tue, 18 May 2004 13:33:24 -0400
To: Andrea Nichols <andrea@plant.mit.edu>,
        "'agallant@mit.edu'" <agallant@MIT.EDU>,
        "'amcgurl@rle.mit.edu'" <amcgurl@rle.mit.edu>, B-Zone <B-Zone@MIT.EDU>,
        Cust-Coach <cust-coach@MIT.EDU>,
        "'fletch1@eecs.mit.edu'" <fletch1@eecs.mit.edu>,
        "'pmorley@mit.edu'" <pmorley@MIT.EDU>,
        "'rroscoe@mit.edu'" <rroscoe@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'wgibbs@rle.mit.edu'" <wgibbs@rle.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
From: Elizabeth D Cooper <edc@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
In-Reply-To: <568F0AEE7A57D511923900508B55645103D72687@plantnt.facilitie
 s.ms.mit.edu>
Mime-Version: 1.0
Content-Type: multipart/alternative;
	boundary="=====================_1289629068==.ALT"

--=====================_1289629068==.ALT
Content-Type: text/plain; charset="us-ascii"; format=flowed

If this could start earlier in the morning, it would be better.  By that 
time of year, it should be quite warm (hopefully), particularly on the 
south side of the building.  fortunately there aren't as many people in the 
building.

I note that building 38 has had 26 shutdown requests since Februrary 
26.  10 of those were for air handlers and one of those was for a whole 
week.  I do hope this is the end of this for a while.

At 01:15 PM 5/18/2004 -0400, Andrea Nichols wrote:

>To:     agallant@mit.edu; amcgurl@rle.mit.edu; B-Zone; Cust-Coach; 
>edc@mit.edu; fletch1@eecs.mit.edu; pmorley@mit.edu; rroscoe@mit.edu; 
>schedule@mit.edu; wgibbs@rle.mit.edu; shutdowns@mit.edu
>
>Cc:     shutdown@plant.mit.edu
>Subject:        Bldg. 38 - Air Handler 3/Supply Fans 3A and 3B Preventive 
>Maintenance Shutdown Request
>
>The following air handler 3/supply fans 3A and 3B preventive maintenance 
>shutdown request       for Bldg. 38 - South Side - floors 1 through 6 
>offices and labs on Wednesday, May 26, 2004 is for your information and 
>comment.  Would you please let me know whether this does or does not meet 
>with your approval.
>
>Thank you.
>
>Andrea Nichols
>Repair and Maintenenance
>8-7872
>
>Status: Normal
>Building: 38 - South Side - Floors 1 through 6 Offices and Labs
>Date: 5/26/2004
>Day: Wednesday
>Time: 7:30 AM - 11:30 AM
>System: Air Handler 3/Supply Fans 3A and 3B
>Duration: 4 hours
>Reason:
>Perform preventive maintenance work on Air Handler 3 and Supply Fans 3A 
>and 3B.
>
>Effect:
>Loss of supply ventilation, supply cooling and supply heating in the 
>above-listed areas during the 4-hour preventive maintenance shutdown period.

Elizabeth Cooper
Administrative Officer
Electrical Engineering and Computer Science
(617) 253-4643
38-435  
--=====================_1289629068==.ALT
Content-Type: text/html; charset="us-ascii"

<html>
<body>
If this could start earlier in the morning, it would be better.&nbsp; By
that time of year, it should be quite warm (hopefully), particularly on
the south side of the building.&nbsp; fortunately there aren't as many
people in the building.<br><br>
I note that building 38 has had 26 shutdown requests since Februrary
26.&nbsp; 10 of those were for air handlers and one of those was for a
whole week.&nbsp; I do hope this is the end of this for a 
while.<br><br>
At 01:15 PM 5/18/2004 -0400, Andrea Nichols wrote:<br><br>
<blockquote type=cite class=cite cite><font face="MS Sans Serif, Geneva" size=2 color="#120000"><b>To:</b></font>&nbsp;&nbsp;&nbsp;&nbsp;
<font face="MS Sans Serif, Geneva" size=2 color="#080000">agallant@mit.edu;
amcgurl@rle.mit.edu; B-Zone; Cust-Coach; edc@mit.edu;
fletch1@eecs.mit.edu; pmorley@mit.edu; rroscoe@mit.edu; schedule@mit.edu;
wgibbs@rle.mit.edu; shutdowns@mit.edu<br>
</font><br>
<font face="MS Sans Serif, Geneva" size=2 color="#120000"><b>Cc:</b></font>&nbsp;&nbsp;&nbsp;&nbsp;
<font face="MS Sans Serif, Geneva" size=2 color="#080000">shutdown@plant.mit.edu</font>
<br>
<font face="MS Sans Serif, Geneva" size=2 color="#120000"><b>Subject:</b></font>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; <font face="MS Sans Serif, Geneva" size=2 color="#080000">Bldg. 38 - Air Handler 3/Supply Fans 3A and 3B Preventive Maintenance Shutdown Request</font> <br><br>
<font face="MS Sans Serif, Geneva" size=2>The following air handler 3/supply fans 3A and 3B preventive maintenance shutdown request&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; for Bldg. 38 - South Side - floors 1 through 6 offices and labs on Wednesday, May 26, 2004 is for your information and comment.&nbsp; Would you please let me know whether this does or does not meet with your approval.<br>
</font><br>
<font face="MS Sans Serif, Geneva" size=2>Thank you.</font> <br><br>
<font face="MS Sans Serif, Geneva" size=2>Andrea Nichols</font> <br>
<font face="MS Sans Serif, Geneva" size=2>Repair and Maintenenance</font> <br>
<font face="MS Sans Serif, Geneva" size=2>8-7872</font> <br><br>
<font face="MS Sans Serif, Geneva" size=2><b>Status:</b></font> <font face="MS Sans Serif, Geneva" size=2>Normal</font> <br>
<font face="MS Sans Serif, Geneva" size=2><b>Building:</b></font> <font face="MS Sans Serif, Geneva" size=2>38 - South Side - Floors 1 through 6 Offices and Labs</font> <br>
<font face="MS Sans Serif, Geneva" size=2><b>Date:</b></font> <font face="MS Sans Serif, Geneva" size=2>5/26/2004</font> <br>
<font face="MS Sans Serif, Geneva" size=2><b>Day:</b></font> <font face="MS Sans Serif, Geneva" size=2>Wednesday</font> <br>
<font face="MS Sans Serif, Geneva" size=2><b>Time:</b></font> <font face="MS Sans Serif, Geneva" size=2>7:30 AM - 11:30 AM</font> <br>
<font face="MS Sans Serif, Geneva" size=2><b>System:</b></font> <font face="MS Sans Serif, Geneva" size=2>Air Handler 3/Supply Fans 3A and 3B</font> <br>
<font face="MS Sans Serif, Geneva" size=2><b>Duration:</b></font> <font face="MS Sans Serif, Geneva">4 hours</font> <br>
<font face="MS Sans Serif, Geneva" size=2><b>Reason:</b></font> <br>
<font face="MS Sans Serif, Geneva" size=2>Perform preventive maintenance work on Air Handler 3 and Supply Fans 3A and 3B.</font> <br><br>
<font face="MS Sans Serif, Geneva" size=2><b>Effect:</b></font> <br>
<font face="MS Sans Serif, Geneva" size=2>Loss of supply ventilation, supply cooling and supply heating in the above-listed areas during the 4-hour preventive maintenance shutdown period.<br>
</font></blockquote>
<x-sigsep><p></x-sigsep>
Elizabeth Cooper<br>
Administrative Officer<br>
Electrical Engineering and Computer Science<br>
(617) 253-4643<br>
38-435 </body>
</html>

--=====================_1289629068==.ALT--