[70467] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg 36 - Supply Fan 7B Shutdown/Filter Change Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Dec 11 07:55:32 2003

Message-ID: <568F0AEE7A57D511923900508B55645103D71E51@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'amcgurl@rle.mit.edu'" <amcgurl@rle.mit.edu>, B-Zone <B-Zone@MIT.Edu>,
        Cust-Coach <cust-coach@MIT.Edu>, Robert Cunkelman <rpc@PLANT.MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'wrgibbs@rle.mit.edu'"
	 <wrgibbs@rle.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 11 Dec 2003 07:52:37 -0500

> To: 	amcgurl@rle.mit.edu; B-Zone; Cust-Coach; Robert Cunkelman;
> schedule@mit.edu; wrgibbs@rle.mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg 36 - Supply Fan 7B Shutdown/Filter Change Request
> 
> 
The following supply fan 7B shutdown/filter change request for Bldg. 36 -
North offices on floors 2 through 8 on Monday, 12/15 is for your information
and comment.  Would you please let me know whether this does or does not
meet with your approval.

Thanks very much.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 36 - North Offices - floors 2 through 8
> Date: 12/15/2003
> Day: Monday
> Time: 12:30 PM - 2 PM
> System: Supply Fan 7B - PM# 702034
> Duration: 1 1/2 hours
> Reason: 
> Filter changes.
> 
> Effect: 
> Loss of supply ventilation, supply cooling and supply heating in the
> above-listed areas during the 1 1/2 hour shutdown/filter change period.
> 
> 

home help back first fref pref prev next nref lref last post