[70452] in Hotline Meeting
Bldg. 36 - Supply Fan 8B Shutdown/Filter Change Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Dec 10 15:04:11 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71E4D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'amcgurl@rle.mit.edu'" <amcgurl@rle.mit.edu>, B-Zone <B-Zone@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, Robert Cunkelman <rpc@PLANT.MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'wrgibbs@rle.mit.edu'"
<wrgibbs@rle.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 10 Dec 2003 15:04:01 -0500
> To: amcgurl@rle.mit.edu; B-Zone; Cust-Coach; Robert Cunkelman;
> schedule@mit.edu; wrgibbs@rle.mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 36 - Supply Fan 8B Shutdown/Filter Change Request
>
>
The following supply fan 8B shutdown/filter change request for Bldg. 36 -
Labs - floors 2 through 8 on Monday, 12/15/03 is for your review and
comment. Would you please let me know whether this does or does not meet
with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 36 - Labs - floors 2 through 8
> Date: 12/15/2003
> Day: Monday
> Time: 10 AM - 11:30 AM
> System: Supply Fan 8B - PM# 702015
> Duration: 1 1/2 hours
> Reason:
> Filter changes.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating in the
> above-listed areas during the 1 1/2 hour shutdown/filter change period.
>
>