[70196] in Hotline Meeting
Bldg. 8 - 120/208 Voltage Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Dec 2 08:46:11 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71DD2@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, "'carolr@mit.edu'" <carolr@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, "'ghughes@mit.edu'" <ghughes@MIT.Edu>,
"'glabonte@mit.edu'" <glabonte@MIT.Edu>,
"'lechtman@mit.edu'"
<lechtman@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 2 Dec 2003 08:42:49 -0500
> To: C-Zone; carolr@mit.edu; Cust-Coach; ghughes@mit.edu;
> glabonte@mit.edu; lechtman@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 8 - 120/208 Voltage Power Shutdown Request
>
>
The following 120/208 Voltage Power shutdown request for Bldg. 8 - Basement
on Thursday, 12/11 PM to Friday, 12/12 AM is for your information and
comment. Would you please let me know whether this does or does not meet
with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 8 - Basement
> Date: 12/11/2003
> Day: Thursday
> Time: 11 PM (12/11) - 7 AM (12/12)
> System: Building Power - 120/208 Voltage
> Duration: 8 hours
> Reason:
> Tie-in new power panels in basement as part of 2nd floor Van Vliet Lab
> Renovation.
>
> Effect:
> Loss of 120V, 208V normal power in Bldg. 8 - Basement. This means that no
> computers, lighting, receptacles or condensate return will be operational
> during the shutdown period.,
>
>