Bldg. 31 - Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jul 11 12:30:26 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F2275@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'jmletend@mit.edu'" <jmletend@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>,
"'thane@mit.edu'" <thane@MIT.Edu>, "'rcf@mit.edu'"
<rcf@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
Billy Homeyer
<whomeyer@PLANT.MIT.EDU>
Date: Fri, 11 Jul 2003 12:30:22 -0400
> To: B-Zone; Cust-Coach; jmletend@mit.edu; shutdowns@mit.edu;
> thane@mit.edu; rcf@mit.edu
> Cc: shutdown@plant.mit.edu; Billy Homeyer
> Subject: Bldg. 31 - Building Power Shutdown Request
>
>
The following building power shutdown request for Bldg. 31 - 053; ground
floor on Thursday, July 24 and Friday, July 25 is for your information and
comment. Would you please let me know whether this does or does not meet
with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7871
> Status: Normal
> Building: 31 - 053; ground floor
> Date: 7/24/2003
> Day: Thursday
> Time: 11 PM (7/24) - 7 AM (7/25)
> System: Building Power
> Duration: 8 hours
> Reason:
> Change-out and relocate power panels in 053.
>
> Effect:
> Loss of building power in 053 and ground floor.
>
>