[66789] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. NW12 - Asbestos Removal Notification

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jul 10 15:31:10 2003

Message-ID: <568F0AEE7A57D511923900508B556451023F2262@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'zone@mit.edu'" <zone@mit.edu>, "'devries@mit.edu'" <devries@mit.edu>,
        "'esico@mit.edu'" <esico@mit.edu>, "'eslau@mit.edu'" <eslau@mit.edu>,
        "'fredmcw@mit.edu'" <fredmcw@mit.edu>,
        "'hallisey@mit.edu'"
	 <hallisey@mit.edu>,
        "'jbernard@mit.edu'" <jbernard@mit.edu>,
        "'opsnote@mit.edu'" <opsnote@mit.edu>,
        "'pbrenton@MIT.EDU'"
	 <pbrenton@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'tr6@mit.edu'" <tr6@mit.edu>, "'jdoucett@mit.edu'" <jdoucett@mit.edu>,
        "'dcosta@mit.edu'" <dcosta@mit.edu>,
        "'jbernard@mit.edu'"
	 <jbernard@mit.edu>,
        "'opsnote@mit.edu'" <opsnote@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
        Operators
	 <Operators@PLANT.MIT.EDU>,
        Walter Latta <walatta@PLANT.MIT.EDU>
Date: Thu, 10 Jul 2003 15:30:57 -0400

> To: 	zone@mit.edu; devries@mit.edu; esico@mit.edu; eslau@mit.edu;
> fredmcw@mit.edu; hallisey@mit.edu; jbernard@mit.edu; opsnote@mit.edu;
> pbrenton@MIT.EDU; shutdowns@mit.edu; tr6@mit.edu; jdoucett@mit.edu;
> dcosta@mit.edu; jbernard@mit.edu; opsnote@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators; Walter Latta
> Subject: 	Bldg. NW12 - Asbestos Removal Notification
> 
> 
The following asbestos removal notification for Bldg. NW12 - 1st floor
(inside Reactor Area) on Friday, July 11 is for your information.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: NW12 - 1st floor (inside the Reactor area)
> Date: 7/11/2003
> Day: Friday
> Time: 7 AM - 4 PM
> System: None - asbestos removal notification
> Duration: 9 hours
> Reason: 
> Must remove 8 feet of pipe insulation in ceiling.
> 
> Effect: 
> Area will be cordoned off during the asbestos removal period.
> 
> 