[66485] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg.NW16 - Air Handler/Supply Fan 3 Shutdown/Filter Change Reque

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jun 18 07:28:27 2003

Message-ID: <568F0AEE7A57D511923900508B556451023F20E7@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: D-Zone <D-Zone@MIT.Edu>, "'fulton@psfc.mit.edu'" <fulton@psfc.mit.edu>,
        "'hrycaj@psfc.mit.edu'" <hrycaj@psfc.mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 18 Jun 2003 07:28:22 -0400

> To: 	D-Zone; fulton@psfc.mit.edu; hrycaj@psfc.mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg.NW16 - Air Handler/Supply Fan 3 Shutdown/Filter Change
> Request
> 
> 
The following air handler/supply fan 3 shutdown/filter change request for
Bldg. NW16 - 2nd floor Northwest on Thursday, June 19 is for your review and
comment.  Would you please let me know whether this does or does not have
your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: NW16 - Northwest side
> Date: 6/19/2003
> Day: Thursday
> Time: 8:30 AM - 9 AM
> System: Air Handler/Supply Fan 2 - PM# 712044
> Duration: 1/2 hour
> Reason: 
> Pre-filter changes.
> 
> Effect: 
> Loss of supply ventilation, supply cooling and supply heating in the
> above-mentioned area during the 30 minute shutdown/filter change period.
> 
> 

home help back first fref pref prev next nref lref last post