[66343] in Hotline Meeting
Bldg. 66 - Fire Protection Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jun 9 07:18:03 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F2054@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'haverty@mit.edu'" <haverty@MIT.Edu>,
"'kkgleasn@mit.edu'"
<kkgleasn@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'swetzel@mit.edu'" <swetzel@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 9 Jun 2003 07:17:55 -0400
> To: A-Zone; Cust-Coach; haverty@mit.edu; kkgleasn@mit.edu;
> schedule@mit.edu; swetzel@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 66 - Fire Protection Water Shutdown Request
>
>
The following fire protection water shutdown request for Bldg. 66 - 1st
floor on Friday, June 13 is for your information and comment. Would you
please let me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 66 - 1st floor
> Date: 6/13/2003
> Day: Friday
> Time: 7:30 AM - 11:30 AM
> System: Fire Protection Water
> Duration: 4 hours
> Reason:
> Relocate hose cabinet West Lobby; demolish sprinkler system in 66-110
> Lecture Hall.
>
> Effect:
> Loss of fire protection water in Bldg. 66 - 1st floor. The Safety Office
> will be advised of this - that office will notify the Fire Department.
>
>